Written Scheme of Examination: What PSSR Requires and What It Contains

The Pressure Systems Safety Regulations 2000 (PSSR, SI 2000/128) require the user of an installed pressure system, or the owner of a mobile one, to have a written scheme of examination (WSE) in place before it is operated. The system must then be examined in accordance with that scheme. The Health and Safety Executive’s (HSE) Approved Code of Practice (ACOP), Safety of pressure systems, is L122.
A WSE is not simply an inspection certificate or a standard template. It is a system-specific plan identifying what needs examining, how and when it should be examined, and what precautions are needed to do the work safely.
Key points
- A competent person must draw up or certify the WSE as suitable.
- The scheme must identify the relevant parts of the system and set the examination method and intervals.
- PSSR does not prescribe a single examination interval for every system.
- A report of examination records findings and required actions; it is not a substitute for the scheme.
- Changes to equipment, its use or operating conditions may mean the scheme needs review.
What pressure systems need a written scheme?
PSSR applies to pressure systems used at work that contain a “relevant fluid”. This includes steam at any pressure and, broadly, gases above 0.5 bar above atmospheric pressure, as well as certain liquids that can produce vapour above that pressure.
A pressure system can comprise a pressure vessel, associated pipework and protective devices. In practice, a site may have one without referring to it as a pressure system: examples include compressed-air receivers, steam boilers, autoclaves, gas-loaded hydraulic accumulators, refrigeration plant and process pipework.
Whether a particular system needs a WSE depends on its configuration, fluid, pressure, volume and any applicable exceptions. For example, PSSR’s WSE examination provisions do not apply to a system containing a relevant fluid other than steam if the pressure-volume product of each pressure vessel is less than 250 bar litres. Steam systems are treated differently. Some refrigeration systems are also excepted, including certain systems with a total installed compressor motor power not exceeding 25 kW.
These are not the only factors to consider. Check the system against the full requirements and exceptions in PSSR and ACOP L122 rather than deciding by equipment name alone. A competent person can help establish whether the system is in scope and where its boundaries lie. See the HSE ACOP L122 and PSSR 2000.
What does a written scheme of examination contain?
Regulation 8 requires the scheme to identify the relevant parts of the system and specify the nature and frequency of examination. ACOP L122 sets out what it should include as a minimum:
- The scope: which parts are to be examined, including relevant vessels, protective devices and any pipework where a defect could give rise to danger.
- Equipment identification: enough detail to match each item in the scheme to the plant on site.
- Examination requirements: the nature of examination for each part, including inspection and testing of protective devices such as safety valves.
- Examination intervals: the maximum interval between examinations for the relevant parts.
- Safe preparation: any specialist measures needed before or during examination, such as cooling, venting, removing insulation or arranging safe access.
- Pre-use examination: whether an examination is required before the system is used for the first time.
- Critical parts: parts that, if repaired or modified, should be examined by a competent person before the system is used again.
- Certification details: the name of the competent person certifying the scheme and the certification date.
The required examination may be in service, out of service, or a combination of both. The scheme should make clear what is appropriate for the particular equipment. For a complex examination, it may also need to specify isolation, depressurisation, removal of contents or cool-down arrangements.

Who prepares the scheme?
Under regulation 8, the WSE must be drawn up, or certified as suitable, by a competent person. The required competence depends on the type, size and complexity of the pressure system. ACOP L122 describes competence in terms of relevant practical and theoretical knowledge, actual experience, access to specialist services and suitable professional support.
A competent person can be in-house or independent. An in-house arrangement needs appropriate independence from the system’s operating functions so that the assessment is objective and impartial. For a complex system, the necessary expertise may need to come from a team rather than one individual.
A general risk assessor or maintenance manager working from an unverified template should not be assumed to have the specialist competence needed to prepare or certify a WSE. A manufacturer may provide an initial scheme, but it still needs to be certified as suitable and considered in the context of the system’s actual installation, condition and duty.
The duty holder remains responsible for ensuring the scheme is in place and suitable. The competent person’s involvement does not remove that responsibility.
How often must a pressure system be examined?
There is no statutory “12 months for everything” rule under PSSR. Regulation 8 requires the scheme to specify the examination frequency, and regulation 9 requires examinations to be completed within those intervals.
The competent person determines suitable intervals using factors such as the system’s history and current condition, expected operating conditions, the fluid and the quality of maintenance and supervision. Different parts of the same system may have different intervals. Protective devices should be examined at least as often as the plant they protect, and some may need more frequent checks.
The reasoning should be appropriate to the system rather than copied without consideration from a supplier’s manual or another site’s scheme. The scheme should also be reviewed periodically by a competent person. Review is particularly important when examination findings or changing conditions could affect its suitability.
What happens during an examination?
The competent person examines the parts identified in the scheme, using suitable techniques to assess their condition and fitness for continued use. The duty holder must make sure the system is safely prepared, including any measures specified in the scheme. Depending on the equipment, that may involve isolation, cooling, venting, draining, removing insulation or providing access.
Afterwards, the competent person produces a report of examination. The report is the record of what was found; the WSE is the plan against which the examination was carried out.
Under regulation 9, the report must identify the parts examined, their condition and the results. It must also state any necessary repairs, modifications or changes to safe operating limits and the deadline for those actions. It specifies the date after which the system must not be operated without another examination, and whether the scheme remains suitable or should be modified.
The report must be sent to the user or owner as soon as practicable and, in any event, within 28 days of the examination, or before the report’s specified action deadline if that comes sooner. Defects and recommendations should be assigned and acted on. The system must not be operated beyond the specified examination date, or past a required repair deadline without completing the work.

What commonly goes wrong with a WSE?
What we see on site: schemes are sometimes reused for another receiver or boiler without checking that it has the same design, duty or condition. Other schemes have not been reviewed after plant has been modified. A supplier’s suggested interval may have been copied without recording why it suits the system.
We also find pressure systems still in operation after an examination has become overdue, or protective devices such as safety valves that have not been functionally tested as required by the scheme. New pipework, a re-rated receiver or a change in operating conditions can also make an existing scheme inaccurate.
Review the scheme with a competent person when:
- pressure equipment, pipework or protective devices are modified or repaired;
- the system’s duty or operating conditions change;
- the system’s use or the premises’ use changes in a way that may affect the system;
- examination findings indicate a change is needed; or
- the competent person recommends a review.
Keep the scheme aligned with the plant: check that equipment identifiers and boundaries still match what is installed, and tell the competent person about relevant changes before the next examination.
Which records must be kept?
Regulation 14 requires the user or owner to keep the latest report of examination and any earlier reports that materially help assess whether the system is safe to operate or whether repairs and modifications can be carried out safely. The duty holder must also keep relevant manufacturer or supplier information and records of any agreed postponement of an examination until a further examination has taken place.
For an installed system, these records must be kept at the premises where it is installed, unless other premises have been approved by the enforcing authority. Electronic records are acceptable if they can be reproduced when required and are protected from loss or unauthorised interference. If responsibility for the system changes, the previous user or owner must pass the relevant records to the new one as soon as practicable.
What is the next step?
Check that each potentially relevant pressure system has been assessed for scope, has a current, system-specific WSE, and has examination dates and actions under control. Safemach supports businesses with PSSR written schemes of examination and pressure system examinations, as well as advice on whether a system is in scope. To discuss a system with a safety engineer, contact Safemach.